03 5437100

info@ultraspec.co.nz

14 McGlashen Avenue, Richmond 7020

Commercial Projects

Save Mart Unit 1

  • Supply and Erection of 1208sq/m Clearspan Formsteel Technologies Building.
  • Four roller doors, PA doors and Tilt panels along the length (56m) of the East side of building.
  • Including earthworks, foundations and pad. Included Gas sealed methane barrier.
  • Novaflow methane vents under pad connecting to rato vents either side of building. Included were 50sq/m of office space.
  • Alucobond and Aluclad feature cladding to office walls.
  • The lightweight nature and strength of the Formsteel technologies buildings are its biggest benefits with regards to its ability to withstand severe seismic activity proven in the Christchurch earthquakes.

Project: Save Mart Unit One

Location: Quarantine Road

Size: 1208 Sqm Warehouse

Completion: October 2014